Summary:
- A practical guide to the documentation and data book requirements for industrial valve procurement — covering what documents must be supplied, how they should be organised, and why complete, accurate documentation is as important as the valve itself.
- Learn exactly which certificates, test reports, material test records, and inspection documents should be required from valve suppliers and what red flags in documentation indicate potential quality or compliance issues.
- Understand how to compile comprehensive valve data books that support safe operation, maintenance, repair, and regulatory compliance throughout the valve’s full service life.
Introduction: Documentation is Part of the Product
When you purchase an industrial valve, you are not just buying a piece of mechanical hardware. You are buying a documented, traceable, certified piece of equipment whose quality and compliance can be verified through its associated documentation. A valve without documentation is a valve of unknown quality and provenance — and in safety-critical, pressure-containing applications, unknown quality is unacceptable quality.
Yet valve documentation is routinely underspecified, incompletely received, and inadequately managed in practice. Procurement teams focus on price and delivery. Inspection teams focus on the physical valve. The document review — the check that the metal is actually what it claims to be, that the tests were actually performed, that the valve was actually manufactured to the specified standard — is skipped or done superficially. The consequences of this negligence can be serious: counterfeit materials, untested valves, and equipment that doesn’t comply with the specifications it’s claimed to meet.
Material Test Reports: The Foundation of Traceability
Certified Material Test Reports (CMTRs) are the most fundamental documents in the valve documentation package. A CMTR provides chemical analysis results and mechanical test results for the specific heat of material used to manufacture each pressure-containing component of the valve. It traces the material from the mill where it was produced to the finished valve, providing assurance that the body, bonnet, disc, and other critical components are made from the specified material grade with the specified properties.
A valid CMTR must include: the material specification and grade (e.g., ASTM A216 WCB); the heat number of the material; the chemical analysis results for all specified elements; the mechanical test results (yield strength, tensile strength, elongation, impact energy where required); the heat treatment condition; the test laboratory identification; and certification by the material manufacturer that the results are accurate and the material meets the specification. A CMTR that simply lists the specification requirements without providing actual measured results is not a valid CMTR — it is a compliance declaration that proves nothing about the actual material in the valve.
Factory Acceptance Test Reports
The factory acceptance test (FAT) report documents the results of all factory tests performed on the specific valve before shipment. For valves tested to API 598 or ISO 5208, this must include: the hydrostatic shell test results (test pressure applied, test duration, observed leakage — “NIL” or actual measured value, not just “passed”); the hydrostatic seat closure test results for each seat; the pneumatic closure test results if specified; the backseat test results if applicable; and the visual and dimensional inspection results.
The FAT report must clearly identify the specific valve(s) to which it applies — by tag number, serial number, or purchase order line number — so that the test results can be unambiguously linked to the specific hardware. Generic FAT reports that don’t identify specific valves are not acceptable — they may represent test results for completely different valves or even fabricated results. Every data point in the FAT report should be an actual measured value, not a target value or a copied specification requirement.
Non-Destructive Examination Records
For valves subject to NDE (non-destructive examination) requirements — typically those in higher pressure classes or safety-critical services — the NDE records must document which examinations were performed, by whom, using which procedure, what equipment was used, and what the results were. For radiographic examination of castings, the actual radiographic films or digital images should be available for review, along with the interpretation report by the qualified radiographer.
NDE procedures must be qualified and documented. The examiner must be certified to the appropriate level (typically Level II or III under SNT-TC-1A or EN ISO 9712). The examination must reference a written procedure that has been qualified against the applicable code requirements. NDE results that simply state “examined, no defects found” without any reference to the procedure used, the equipment calibration, or the examiner’s qualifications are not adequate documentation.
Certificate of Conformance
The Certificate of Conformance (CoC) is the manufacturer’s formal declaration that the valve was designed, manufactured, inspected, and tested in accordance with the specified standards and the purchase order requirements. It should be signed by an authorised representative of the manufacturer — not a generic stamp or an unsigned copy. The CoC should specifically reference the applicable standards (e.g., API 6D, 23rd Edition; API 598, 10th Edition), the purchase order number, and the valve tag numbers or serial numbers to which it applies.
A CoC received without supporting documentation — CMTRs, FAT reports, NDE records — is essentially worthless. It is a self-declaration without evidence. For critical applications, the CoC is the summary document that brings together all the supporting documentation; it means nothing in isolation.
Installation, Operation and Maintenance Manuals
Every valve must be accompanied by an Installation, Operation and Maintenance (IOM) manual that provides the information needed to install, operate, and maintain the valve safely and correctly. The IOM should include: installation instructions (orientation requirements, flanging and bolting procedures, pressure testing requirements); operating instructions (correct operating procedure, speed of operation, torque requirements); maintenance instructions (packing replacement procedure, seat reconditioning, lubrication requirements); spare parts list with part numbers and drawings; and troubleshooting guidance for common problems.
IOM manuals that are clearly generic — not specific to the valve type and size supplied — are inadequate. The instructions must be specific enough to be actually useful to a maintenance technician working on the specific valve in the field. Critical safety warnings (such as “do not remove packing while valve is under pressure”) must be clearly prominent and not buried in small print.
Compiling the Valve Data Book
All of the above documents — and any others required by the project specification — should be compiled into a comprehensive valve data book for each valve or valve package. The data book is the permanent record of the valve’s design, materials, manufacture, and testing that supports safe operation and maintenance throughout the valve’s life, and enables future inspection programmes, life extension studies, and replacement decisions to be made on the basis of actual documented evidence rather than assumptions.
Organise the data book logically: general information and summary first, then design documents, then manufacturing records (CMTRs, welding records, heat treatment records), then inspection and NDE records, then FAT reports, then the Certificate of Conformance, then the IOM manual and spare parts information. Index the contents clearly so that specific information can be found quickly when needed. Store the data book in a secure, accessible location — typically in the plant’s document management system — and link it to the equipment tag in the computerised maintenance management system (CMMS).
Conclusion: Good Documentation Costs Nothing Extra
The cost of specifying and receiving proper valve documentation is essentially zero — the documentation is part of the product you’re paying for, and any manufacturer who cannot or will not provide it is telling you something important about the quality of their product. Specify the documentation requirements clearly in every valve purchase, insist on receiving them at or before delivery, review them critically, and file them permanently. This discipline will save you from expensive problems and give you the confidence that comes from knowing exactly what you’ve installed.